BAHAWALPUR GRID STATION

November 15, 2015
0 Comments
Construction of 02 No. 220KV line bays, along with switchyard trenches, etc. at 220/132KV Grid station Bahawalpur.
Total project cost was PKR. 29 million.
The project was awarded by NTDC and executed in 2015/16 by Zahid and company.